"name": "刘振华",
"record_count": 2,
"records": [
{
"id": 3,
"task_id": 2,
"task_name": "窑尾高温风机变频器参数校验",
"task_status": "已完成",
"start_date": "2026-09-02",
"start_half": "AM",
"end_date": "2026-09-02",
"end_half": "PM",
"participants": [
"刘振华",
"杨明辉"
],
"remark": "参数回读、空载试车",
"created_at": "2026-09-01T08:30:00+08:00",
"updated_at": "2026-09-12T17:20:00+08:00",
"version": 1
},
{
"id": 5,
"task_id": 5,
"task_name": "6kV 高压开关柜绝缘测试",
"task_status": "已完成",
"start_date": "2026-09-01",
"start_half": "AM",
"end_date": "2026-09-02",
"end_half": "PM",
"participants": [
"李建军",
"刘振华",
"杨明辉"
],
"remark": "停电测试,恢复送电",
"created_at": "2026-09-01T08:30:00+08:00",
"updated_at": "2026-09-12T17:20:00+08:00",
"version": 1
}
]
}